Update to Giles Tait (KO) Conflict
- Barry Murphy
- Oct 13, 2023
- 3 min read
Updated: Nov 28, 2023
This update is a followup to the Conflict Of Interest (COI) we discovered with a lead engineer working on the Teitei Drive Kāinga Ora Project. If you haven't read it yet, click here.
Giles Tait held the roles of "Project Manager" and "Delivery Lead" and procured third party contractors and signed authority for hundreds of thousands of dollars worth of spend on the project. Kāinga Ora continue to talk down his role in the project, however we have obtained the signed agreements and some of his delegations

On 25th July, Giles Tait & Renee Regal from Kāinga Ora had a zoom call with myself and one other. They agreed the call could be recorded & during that call, Giles stated information about Cordyline place as if he knew the area very well. At no point did he state he had a conflict, or that he owned a property in that street, funny enough Renee Regal was not aware of the conflict until we brought it to KO's attention on the 4th August; Giles only completed official documentation on the 7th August registering his conflict.
Kāinga Ora claims Giles made a verbal COI to his manager on 27th October 2022, though no official paper work was filled out, no emails were sent to anyone and no managers or any other staff were advised of the conflict.
In January 2023, Stage 1 design was modified to extend to Giles property, where a reserve was placed following a contour map, we believe Giles has told them a running stream was present. When we have questioned the matter, we have been pointed to an ecologist report in the resource consent for evidence, but nothing is of use or present about this stream. It's noted that the overgrowth didn't allow an inspection of the particular area. Evidence also shows that Giles instructed personal to extend a stream on the design drawings and provided them the contour map.
Giles was since removed from the project since September with Kāinga Ora saying it wasn't an admittance of guilt, but to protect the individual and the project. They have not released any details into the investigation, however we have found some information and a timeline from the OIA documents we have obtained.
This seems like a conflict to meet in person and not do it via email for record keeping. This is after the COI has apparently been lodged, but perhaps before it's officially lodged in the main database. As we have not been privy to the COI lodged by Mr Tait, we can only assume this is to get the wording right for the submission. Especially after all the email threads and concerns of conflict.
It is then recommended that compliance week is coming up and that all staff members should be sat down one by one to ensure they are aware of their obligations. This goes against what the media has reported and Kāinga Ora have stated, that Giles COI was registered due to the annual filing, it was still a week out from actual compliance week.
The claim that the reserve was built due to contours or stormwater is not fact, they have built a road over it in the design, the snowmass developer has confirmed it can be infilled and built on.
There is no supporting documentation other than a contour map showing an old stormwater erosion; the ecological and environmental documents show a manually drawn on additional stream.
Design drawings were updated at the request of Giles Tait (email 6th April) to add a stream to the drawings.
Statistics of OIA's submitted


Comments